Merchant Taylors School – Site Progress

Date posted: November 27, 2014

The new Design and Technology and Art building for Merchant Taylors’ School is progressing well on site, managed by main contractor Borras Construction. Works in the ground and the superstructure are now complete, current works include completing the external envelope and first fix for mechanical and electrical services. The programme is on schedule for completion next Summer. Many thanks to Borras for allowing us to host this time lapse video showing progress thus far.