Mayflower Halls, Southampton

Date posted: September 3, 2013

Construction of Mayflower Halls student residence is continuing apace, and the works remain on target for completion in summer 2014. The post tension concrete frame is now complete on two blocks, with the third due for completion early 2014. The occasion will be marked by a topping-out ceremony in February. Many floors are now watertight, thanks to the fast track installation of the SIPS panel system, allowing internal fit-out to progress. Externally, brickwork, windows and curtain walling are currently being installed, with cladding panels due to commence shortly.